GUIDE · MATERIAL FLOW

What Is Mixed Model Material Flow?

Mixed Model Material Flow is the design of how every part reaches the line: the right part, in the right container, in the right sequence, at the right location, in the right quantity, at the right time, at the right total cost. It is the second wing of Lean. A beautifully designed line cannot fly without it.

By Richard Rahn and Gerard Leone · 13 minute read

The short answer

Material Flow is a system for getting parts from suppliers to the point of use, based on what is actually consumed. It combines a plan for every part, visual pull signals, calculated inventory quantities, right-sized containers, scheduled delivery routes and suppliers who respond to the same signals. Done well, the operator never goes looking for a part and the line never stops waiting for one.

We call it mixed model because the same system has to serve many products, with different parts, in whatever mix is built that day. That is what makes the design interesting, and what makes simple rules of thumb fail.

The two wings of Lean

Think of Lean as a bird. Value stream and line design are one wing. Material flow is the other. Line design maps and balances the work. Material flow makes sure the right parts are standing at every workstation when the work arrives. Remove either wing and the bird goes in circles.

Unfortunately, material flow is too often treated as a second-class citizen. A line is designed with great care, and then the materials people are told to "just get the parts there". The result is shortages, line stoppages, wasted space and a very busy forklift. The material team deserves the same engineering attention as the line itself, because its work is strategic, not just operational.

Push, pull and flow

Three words need to be clear before anything else.

• Push. Materials arrive because of a forecast, which is sometimes a polite word for a guess. Think of a gas station making sandwiches in the morning and hoping they sell by evening.

• Pull. Materials arrive in response to a signal tied to real consumption. A burger restaurant keeps a limited number of burgers ready and makes more as they sell. It anticipates demand, but it caps the risk.

• Flow. The most advanced form of pull. Materials arrive one at a time, or in very small batches, in line with the actual order. A sandwich shop that makes your sandwich after you order it is flow.

If you supply parts from a computer-generated list on a preset schedule, you are pushing, whatever the poster in the break room says. Computers can support pull, but a pull signal is about real-time consumption, not a database record. If inventory accuracy slips or a transaction is late, the computer is wrong. A human looking at an empty bin is never late. That works only with discipline, accountability and a little extra inventory, none of which happen automatically.

The seven rights

Every material system exists to deliver seven things. When any one is wrong, someone pays for it.

• The right part, including the right revision level.

• The right container, the one assigned to that part, sized to actual usage.

• The right sequence, where parts are delivered in the order the line will use them.

• The right location, the assigned point of use. A part in the wrong place costs effort at best and a stopped line at worst.

• The right quantity, usually a small, calculated move quantity.

• The right time. Too early takes unplanned space. Too late stops the line. Delivery routes should run like a streetcar, on a fixed schedule.

• The right total cost. Cutting material handlers to save labor can raise shortages and inventory. Measure the whole system, not one department.

Why this matters more now

Supply chains have grown long and complicated. Product variety has exploded. Volatility is the new normal, and the pandemic made every executive aware of how fragile a supply chain can be. Yet the underlying questions have not changed: quality, lead time, cost, productivity and waste. Good material flow is still the bedrock. Without clear part identification, responsive inventory policies, sensible containers, efficient routes and suppliers who are part of the system, even the smartest machines and the best people get dragged into poor performance.

A place for everything

Before any signals, give every part a formally defined home. "A place for everything and everything in its place" sounds like a poster, but the payoff is practical. Operators stop searching. Space is used well. Quality checks become systematic, because a part that is out of place is easy to spot. New employees learn faster, and the plant is safer. Store material on a first-in, first-out basis so that old stock leaves before it goes obsolete or deteriorates, and keep traceability simple if a supplier batch turns out to be a problem. Watch out for land-locked parts, which are buried behind other pallets and cannot be reached without moving everything in front of them.

A plan for every part

The foundation is the Plan For Every Part, or PFEP. It is a complete material flow profile for every item that must be handled, purchased or manufactured. "Every item" means every item. One missing inexpensive washer can halt a production line.

A PFEP records, for each part, who supplies it and how long it takes, how and where it is stored, how it is replenished and how often, who handles it, where it is consumed and how it is checked. It starts life as a spreadsheet and graduates to a database as the part count and the number of users grow. Above all, it needs owners. A PFEP that nobody maintains is a very expensive historical document.

Once it exists, the PFEP pays you back. It shows which parts have long lead times, which inventories can shrink, which storage locations hurt ergonomics and which data keeps going wrong and needs more frequent counting.

Pull it with kanban

Kanban is a Japanese word for a visual signal. In materials management, a kanban signals that more material is needed because material was used. An empty bin is a kanban. So is a card on an empty bin, a colored flag, a light, or an electronic message. Operators never order anything. The empty bin does it for them.

The inspiration was the American supermarket: small quantities on a shelf at the point of use, refilled from a warehouse as customers pick items. We use the same idea on the factory floor, and we draw four kinds of locations in a kanban chain:

• Warehouse, a controlled location where every movement is transacted.

• Supermarket, a kanban-controlled inventory on the floor near the line. It is not just a staging area. Parts are pulled into it, never pushed.

• FIFO lane, space for more than one unit, kept in first-in, first-out order. A lane that holds one piece is an in-process kanban.

• Point of use, where the part is consumed.

How much to stock

Quantities should come from time, not from guesswork. The question at every point in the chain is how much supply is needed to last until the next delivery. Small, cheap, fast-moving parts can carry days of supply. Bulky, custom or expensive parts should carry only hours. The basic kanban quantity formula is:

Kanban Amount = (Daily Usage × Safety Factor × Days on Hand) ÷ Container Size

Take a part that uses 134 pieces a day, with a 10 percent safety factor and a target of half a day at the point of use. That is 134 × 1.1 × 0.5, or 74 pieces. In a classic two-bin system, each bin holds 37. When the first bin empties, it signals replenishment while the second bin keeps the line running. Move one link up the chain, and the supermarket might hold two days of supply. The pattern is always the same: a little at the point of use, more as you move upstream.

Choose the right signal for each part

There is no single best method, and most plants end up with a hybrid. There are four basic approaches, each matched to the part:

• Kanban, one to many. A common part, such as an M5 screw used by several products, becomes one standard part number replenished from a shared supermarket. Pooling the demand cuts inventory and simplifies purchasing.

• Part sets, one to many. Parts that always travel together, such as a bolt and its nut, are handled as a single set. That halves the bin space and guarantees a match.

• Kitting, many to one. Many parts are gathered into one kit for one product. A chair station that needs twenty different parts needs one presentation position instead of twenty bins. Kitting costs labor, so weigh it against the benefit.

• Sequencing, one to one. Large or custom parts are delivered one at a time, in the order of the line-up. Think of door assemblies arriving in the color sequence of the vehicles on the line. There is no supermarket and no line-side inventory, but it demands very consistent production.

Even a single item may deserve hybrid handling. Standard hydraulic cylinders used on every model can be kanban at the point of use, while the unique colored ones are kitted or sequenced. Match the method to the part's volume, variability, size and commonality.

Containers and presentation

Containers are not packaging. They are part of the process. Right-sized containers keep replenishment from triggering too often or too rarely, protect the part, and let the operator reach it easily. At the point of use we want inventory based on real demand, the smallest practical footprint, materials within immediate reach, and a service aisle behind the workstation so that replenishment never interrupts the work. Carts, racks and shadow boards make this visual and almost mistake-proof.

Delivery routes: the taxi and the streetcar

There are two ways to move material around a plant. The taxi is the forklift: any point to any point, on call. It is flexible, and it also produces empty return trips, congestion and a hectic floor. The streetcar is the tugger: a fixed route, on a fixed schedule, with defined stops. Planned in detail and run to standard work, it behaves like a Swiss watch, and it lets you calculate staffing and inventory instead of guessing them.

Delivery frequency matters more than most people think. Even small increases in frequency can lower inventory and storage space significantly, though they can raise transport cost, so the balance needs a calculation. And do not design routes on paper alone. Walk them, with the material handlers beside you.

Suppliers belong in the loop

A pull system that stops at your dock only does half the job. Extend the signal upstream. Suppliers who replenish against consumption, local suppliers with milk run deliveries, smaller batches and mixed containers all shorten the chain and cut inventory. Relying on purchase orders and MRP alone will always restrict how quickly you can respond.

Count what counts

A word on measurement. Financial reporting values inventory in dollars, and that is right for the accountants. But a dollar total can be perfectly accurate while the plant is short of the parts it needs this afternoon, because the money is tied up in slow movers and the fast movers ran out. For running the floor, count units: the right parts, in the right condition, in the right amount, at the right time. It is a more honest picture of whether the system is working.

What you get

• Fewer shortages. Zero is the North Star. You will not reach it, but you will always know which way to walk.

• Less inventory and floor space. Smaller quantities, delivered more often.

• Faster inventory turns, measured as Cost of Goods Sold divided by average inventory.

• Less waste in inventory, motion, transportation and waiting.

• A system that adapts. When usage changes, supply follows the signals, and volatility stops distorting the flow.

Mistakes we see most often

• Oversized batches and containers, bought for the convenience of the supplier or the buyer.

• Treating the computer record as the pull signal.

• Cutting material handlers to save labor, then paying for shortages in lost output.

• Leaving parts without a defined location, or storing them where they become land-locked behind other pallets.

• Designing routes in an office, without walking them.

Where to learn it

We teach the full method in our Mixed Model Material Flow workshop, hosted by Toyota Material Handling, with a factory tour so you can see it working. The method is also in our book, Material Flow: The Complete Guide to Mixed Model Material Management.

Material flow serves a line, and the line has to be designed first. Read our companion guide, What Is Mixed Model Line Design?

Learn it with us

Join a hands-on workshop at Toyota Material Handling, or book a 30-minute call to talk about your own line.